Step by Step Guide to Applications

|
Find out if you require a Building Permit before carrying out any works. Its as simple as contacting Banyule BPi or click here for more information.
|
|
Prepare the drawings of the proposed works.
It is advisable to seek the assistance of a registered architect or draftsperson who has knowledge of the relevant Building Regulations and Building Code of Australia. This will ensure that the plans are accurate, clear and concise.
The drawings should include accurate site plans at a Scale of 1:200 or 1:500, Floor Plans, Elevations and structural details at a Scale of 1:100.
If the structural details are prepared by a registered engineer a copy of the computations and structural drawings are to be provided.
|
|
Once the plans and structural details are completed, you are then ready to make an application for a Building Permit
|
|
All applications are processed by our professional Building Surveying staff who ensure that the proposal will meet the requirements and objectives of the Building Regulations and associated Standards.
|
|
When the Building Permit is issued, work is required to commence within 12 months and to be completed within 24 months of the permit issue date.
The time may be extended if an application is made to the Building Surveyor before the expiration date.
|
|
The builders responsibility is to build in accordance with the Building Permit and approved plans and proper work practices.
Any variation to the approved plans must be submitted to the Building Surveyor for approval before the works are carried out.
|
During the construction of your project there are various stages that the Building Surveyor is required to inspect. These are itemised on your Building Permit. These are mandatory inspections and must be looked at.
Inspections are carried out Monday to Friday. Inspections are required to be booked 24 hours prior.
You can book an inspection on 9433 7777.
|
When works are completed you or your builder will request a final inspection to be carried out. The Building Surveyor will then arrange for an inspection to be carried out.
If the building is suitable to occupy for it's intended use an Occupancy Permit or Certificate of Final Inspection will be issued.
The Building Surveyor will send a copy of the relative party. A building cannot be occupied unless an occupancy permit is issued. If a person occupies a building without the issue of an Occupancy Permit, they are not only illegally occupying the building but may not be covered by insurance.